TONGYANG Amends Gwangyang Biomass EPC Contract: Increases Amount to 57.8 Billion Won and Extends Period
TONGYANG Inc has filed an amendment to its contract with Lotte Engineering and Construction for the fabrication, supply, and installation of FGTS and AHS for the Gwangyang Biomass Power Plant EPC project.
The contract amount has been increased from 55.49 billion won to 57.78 billion won, an increase of approximately 2.29 billion won, and the contract end date has been extended from June 30, 2026 to September 30, 2026, a three-month extension.
This increase represents about 1.9% of TONGYANG's market capitalization, while the total contract value amounts to 7.53% of its 2022 consolidated revenue, indicating a limited impact on the company's financials.
The counterparty is Lotte Engineering and Construction, a major domestic construction firm with high creditworthiness, implying low counterparty risk.
[AI Summary]The amendment to TONGYANG's Gwangyang Biomass EPC contract involves a minor increase in contract value and a schedule extension, resulting in a neutral impact on the stock price. It is a routine change within the ongoing project, with no additional financing or dilution effects, and supports stable project execution.
KOSPI Filing Information
[Correction of Description] Conclusion of Single Sale and Supply Contract