SAMIL C&S extends contract period with POSCO E&C for Yeongjong-Cheongna road construction by one month, limited financial impact


  • SAMIL C&S has signed an amendment to extend the end date of its construction contract with POSCO E&C for the Yeongjong-Cheongna road connection project, from May 31 2026 to June 30 2026, a one-month extension.
  • The contract value remains unchanged at KRW 88.4 billion, representing 39.4% of 2021 revenue. The modification is purely an administrative timeline adjustment with limited impact on financials or profitability.
  • POSCO E&C is a top-tier domestic construction firm with high creditworthiness, resulting in low counterparty risk.
  • This event has no direct relation to capital changes or shareholder return policies.
  • [AI Summary]The extension of SAMIL C&S contract period for the Yeongjong-Cheongna road project is a routine administrative adjustment with no change to revenue or earnings estimates, resulting in a neutral impact on shareholder value. While the relationship with high-quality counterparty POSCO E&C continues stably, it does not provide significant stock price momentum.

KOSPI Filing Information


  • [Correction of Description] Conclusion of Single Sale and Supply Contract
  • Company: SAMIL C&S (004440)
  • Submission: SAMIL C&S CO.,LTD
  • Under KRX KOSPI Market Division

  • Shares: 12,731,947
  • Price: 4,900 KRW
  • Market Cap: 62.4 B KRW