Kye-Ryong Construction Increases Cheonan Station Urban Regeneration Contract Amount to 85.71B KRW, Revenue Share Expands to 3.35%


  • Kye-Ryong Construction increased the contract amount for the Cheonan Station Urban Regeneration Innovative District construction project from 81.39B KRW to 85.71B KRW, a rise of 4.31B KRW (5.3%). The total project value is 198.53B KRW, with Kye-Ryong's stake at 43.17%.
  • This amendment reflects the upward revision in contract value, with the revenue contribution ratio slightly improving from 3.18% to 3.35%, indicating a positive order backlog effect.
  • The contract period is from June 2022 to May 2028, a long-term project. Only the amount was adjusted without changes in other conditions, which is favorable.
  • However, this is merely an expansion of an existing contract and is unlikely to have a significant short-term impact on stock price.
  • [AI Summary]Although the contract increase expands the order book, its proportion relative to market cap is modest and the project is long-term, so the impact on shareholder value is limited. However, it may contribute to stable revenue growth in the medium to long term.

KOSPI Filing Information


  • Filing: [Correction of Description] Conclusion of Single Sale and Supply Contract
  • Company: KYE-RYONG CONSTRUCTION INDUSTRIAL (013580)
  • Submission: KYE-RYONG CONSTRUCTION INDUSTRIAL CO.,LTD
  • Receipt: 06-01-2026
  • Under KRX KOSPI Market Division