Insan Inc. Extends New Facility Investment Completion Date by Six Months Due to Permit Delays; No Change in Investment Amount
The completion date of the factory construction has been extended from June 30, 2026 to December 31, 2026 due to administrative permit delays.
The total investment amount of KRW 32.37 billion representing 61.8% of equity remains unchanged, with no new capital raising or dilution risk.
The investment is for building a new production factory in the Hamyang specialized agricultural industrial complex, funded by internal reserves and external financing.
[AI Summary]This amendment is a routine procedural update due to permit schedule delays, with no change in investment scale or terms. No material impact on shareholder value.