BMT Decides on 19.8 Billion KRW Investment for Jangan 2nd Plant to Expand Production Capacity


  • BMT is investing 19.8 billion KRW to construct the Jangan 2nd Plant in Busan to expand production capacity.
  • The investment amounts to 16.09% of equity and will be funded through sale of idle land and bank borrowings.
  • The completion date has been extended by two months to August 31, 2026, due to construction conditions.
  • [AI Summary]BMT's capital expenditure on factory expansion is a productive use of funds without diluting existing shareholders. While financing through asset sales and debt may increase financial leverage, it supports long-term growth and capacity enhancement.

KOSDAQ Filing Information


  • [Correction of Description] Investment in New Facilities, etc.
  • Company: BMTCo (086670)
  • Submission: BMTCo.,Ltd.
  • Under KRX KOSDAQ Market Division

  • Shares: 9,925,885
  • Price: 15,020 KRW
  • Market Cap: 149.1 B KRW