BHI

BHI signs 188.3 billion KRW LNG combined cycle power plant supply contract - secures growth momentum with overseas order equivalent to 24.3% of sales


  • BHI has signed a 188.3 billion KRW (approx. $125.06 million) contract with Toshiba Plant Systems and Services Corporation for the supply of LNG combined cycle power generation equipment, representing a large-scale order equivalent to 24.3% of its 2025 consolidated sales (774.1 billion KRW).
  • The contract period runs from May 29, 2026 to April 30, 2033 (approximately 7 years), with advance payment terms and payment due within 30 days of invoice receipt.
  • This overseas project will be executed through BHI's own production, and the contract amount and period may vary depending on project progress.
  • [AI Summary]This major LNG power plant order is a positive signal for BHI's overseas business expansion and revenue growth, contributing to increased order backlog and stable cash flow generation. However, given the long-term nature of the contract, investors should consider risks from currency fluctuations and potential construction delays.

KOSDAQ Filing Information


  • Filing: Conclusion of a Single Sales and Supply Contract
  • Company: BHI (083650)
  • Submission: BHI Co., Ltd.
  • Receipt: 06-01-2026
  • Under KRX KOSDAQ Market Division