Contract Period Extended by 3 Months for Hyundai E&C's Hanadream Town Interior Work... Contract Amount Unchanged at 12.67B KRW (8.6% of Sales)
SIGONG TECH corrected the contract period for the interior work (Package 3) at Hanadream Town Group Headquarters with Hyundai E&C, extending from May 31, 2026 to August 31, 2026 (3 months).
The contract amount remains unchanged at 12.671 billion KRW (8.6% of 2024 sales of 147.146 billion KRW), with no conditional terms or advance payment.
The project is ongoing in Incheon Seo-gu, performed by SIGONG TECH through self-production (subcontract).
This extension is a routine adjustment to the construction schedule, not a new order or expansion, thus limited impact on shareholder value.
[AI Comprehensive Analysis]This disclosure is merely a schedule change for an existing contract, unrelated to new revenue generation or margin improvement, and is considered a neutral event for the stock price.
KOSDAQ Filing Information
Filing: [Correction Of Description] Conclusion Of Single Sales And Supply Agreement (Voluntary Disclosure)