Amendment to Extend Contract Period for 500kV Dongseoul Substation Civil Works (KRW 73.4bn)
Amendment to extend contract period for 500kV Dongseoul Substation civil works: end date changed from 2029-08-30 to 2030-01-02 (approx. 4 months extension), contract amount KRW 73,371,983,079 (3.89% of 2024 consolidated sales)
Counterparty: Korea Electric Power Corporation (no relationship)
Payment terms: no advance payment, progress payments based on completion
Location: San2, Gamil-dong, Hanam-si, Gyeonggi-do (within Dongseoul Substation site). Main works: earthwork (excavation 107,935㎥, underground power duct 335.32m, piling 4,341m) and building construction (1 basement, 3 floors, 500kV indoor non-standard substation)
Contract period and amount are subject to change as per contract conditions