Correction: Increase in Contract Amount and Extension for Fishery Food Export Complex Construction
-
Contract amount increased to 23.56 billion won (from 22.68 billion), up 3.9%, representing 12.1% of revenue (previously 11.6%)
-
Total project cost of 48.08 billion won, company's 49% share unchanged
-
Contract end date extended to July 31, 2026 (from May 27, 2026), a 2-month extension
-
Counterparty: Public Procurement Service (Mokpo, Jeonnam), construction of fishery food export complex
-
No changes to other terms (advance payment, progress payments, etc.)