LS Electric Revises Contract for North America Data Center Fuel Cell Power Supply (Adds Advance Payment)
LS Electric's subsidiary LS ELECTRIC AMERICA awarded project from Bloom Energy to supply fuel cell power equipment for North American data centers (contract value 318.96 billion KRW, 6.42% of sales)
Correction reason: change in major contract conditions (advance payment: none → exists)
Contract period: 2026-04-28 to 2027-03-29
LS Electric supplies switchgears and distribution transformers to its subsidiary
Exchange rate applied: 1,473.10 KRW/USD for USD 216,526,100
Payment terms: invoicing based on product delivery schedule
Contract amount and period subject to change
KOSPI Filing Information
Filing: [Correction of Description] Conclusion of Single Sales and Supply Contract (Major Management Matters of Subsidiary)