Correction of Contract Period Extension and Payment Terms for Hwaseong-Dongtan Road Construction
-
Contract end date extended by 1 year: 2026-06-30 → 2027-06-30
-
Payment terms changed: no advance payment, progress payments specified
-
Contract amount unchanged at KRW 32,991.6 million (80% share of total KRW 41,239.5 million, VAT incl.)
-
Contract amount equals 20.99% of 2018 revenue (KRW 157,172.9 million)