Correction to Battery Assembly Line Equipment Contract: Extended Deadline and SAT Preparation
Total contract amount approximately 12.44 billion KRW (EUR 8,815,647, adjusted from EUR 9,996,731, 10.92% of recent sales)
Contract end date extended from 2026-05-15 to 2027-01-31 (correction due to customer request)
Equipment delivered and currently preparing for SAT (Site Acceptance Test)
Contract fulfillment rate 56.70% (based on amount received as of disclosure date)
Payment terms: 5% down payment (PO issuance), 5% first milestone (design approval), 40% second milestone (FAT completion), 30% third milestone (SAT completion), 20% final (final inspection)
Counterparty information undisclosed for trade secret protection; contract is not conditional (fixed contract)